TEMPORARY TRAFFIC DECK OVER BRACED EXCAVATION. IN: PREPARING FOR CONSTRUCTION IN THE 21ST CENTURY, PROCEEDINGS OF CONSTRUCTION CONGRESS '91, SPONSORED BY THE AMERICAN SOCIETY OF CIVIL ENGINEERS IN COOPERATION WITH THE AMERICAN INSTITUTE OF MINING ENGINEERS AND THE AMERICAN ARBITRATION ASSOCIATION, CAMBRIDGE, MASSACHUSETTS, APRIL 13-16, 1991

1991 
A case history is used to examine the planning, design, and installation of a temporary traffic deck over a 23-foot-deep braced excavation. The deck was installed in a three-phase sequence to allow traffic to continue on a major city roadway during excavation and the nine-month construction period. The temporary roadway deck consisted of 2000 square feet of timber decking supported by steel girders. The temporary traffic deck system is evaluated in terms of performance, constructability, and safety.