Time-cost trade-off analysis of a priority based assignment problem
2020
In this paper, a bi-objective priority based assignment problem (BPBAP) related to an industrial project, is considered in which, depending upon the work breakdown structure, the n tasks involved in the project are divided into two categories. One of the categories consists of m primary tasks and the other one consists of $$(n-m)$$
secondary tasks (for $$m