Commissioning of Upgrading Reconstruction Project of Taihu Xincheng Wastewater Plant in Wuxi

2010 
The micro-flocculation filtration process is adopted in the upgrading reconstruction project of Taihu Xincheng WWTP in Wuxi.Some problems appearing during the commissioning and trial operation are analyzed,and a series of measures to solve these problems are introduced.The monitoring data indicate that the process is stable and reliable in operation,and the effluent quality reaches the first level A criteria specified in Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant(GB 18918-2002).