Analysis of delays in Tanzanian construction industry
2017
Purpose
The purpose of this paper is twofold: first, to develop theoretical underpinnings using TCE, and second, to run the analysis using an advanced tool such as structural equation modeling (SEM).
Design/methodology/approach
This study was conducted in the construction industry in Tanzania. A questionnaire-based survey method was used. A total of 308 respondents participated in the study. The relationships between the cause and effect factors were analyzed using SEM.
Findings
The important findings are as follows:cost overrun can be explained by consultant-related and material-related factors; disputes can be explained by cost overrun; arbitration can be explained by consultant-related, cost overrun, and dispute factors; litigation can be explained by client-related, disputes, and arbitration factors; and abandonment can be explained by consultant-related, external-related, disputes, arbitration, and litigation factors.
Originality/value
The main contributions of this study are theoretical development and comprehensive analyses of “cause” and “effect” factors of delays in the construction industry.