Implementation plan for the Operations Center Upgrade project

1996 
The crossover from the existing TA-55 Facility Control System to a newly constructed system will be implemented over a four-month period beginning the first week in January, 1997. Personnel requirements and task duration have been established using planning and scheduling project management techniques. Each facility subsystem will be crossed over on individual four-day maintenance weekends during which building PF-4 will be exclusively reserved for these tasks. Each subsystem will be validated prior to the resumption of normal programmatic activities. PF-4 will be open for normal activities between each four-day maintenance weekend. Crossover will not begin until specifically outlined tasks are completed.