This interim report describes the work performed in the Emergency Operating Procedure Tracking System project through December 1986. An Executive Summary (Part 1) provides a high level description of the application and project task description; Functional Specifications (Part II) and Detailed Design Specifications (Part III) give a detailed description of the form and function of the Emergency Operating Procedure Tracking System software. Appendices containing a complete compilation of the rules logic, output messages and version of the Kuo Sheng plant emergency operating procedures are used as a source in the full prototype implementation.