ABSTRACTThis paper aims at clarifying the potential and the limit of the method to surmise the timing of the containment vessel (CV) failure utilizing the Emergency Action Levels (EALs) issued as a nuclear operator’s notification in an early phase of the severe accident (SA). We analyzed the timings of the EALs issued in all kinds of the SA sequences of several PWR plant models by using the SA analysis code, MAAP. We found high correlations between the timing of SE41 (EAL issued at CV pressure of 0.5 design pressure) and the timing of the CV failure in the typical scenarios, e.g. over-pressure failures. We could therefore establish an evaluating method to estimate the time for a CV failure. This method has the potential to support the decision-making in nuclear emergency preparedness.