Power routing: dynamic power provisioning in the data center

2010 
Data center power infrastructure incurs massive capital costs, which typically exceed energy costs over the life of the facility. To squeeze maximum value from the infrastructure, researchers have proposed over-subscribing power circuits, relying on the observation that peak loads are rare. To ensure availability, these proposals employ power capping, which throttles server performance during utilization spikes to enforce safe power budgets. However, because budgets must be enforced locally -- at each power distribution unit (PDU) -- local utilization spikes may force throttling even when power delivery capacity is available elsewhere. Moreover, the need to maintain reserve capacity for fault tolerance on power delivery paths magnifies the impact of utilization spikes.