Start-up challenge

2004 
Start-up during 2002 of the Gebze, Adapazari and Izmir combined cycle power plants in Turkey revealed over-pressure at the boiler feedwater pump discharge. The over-pressure was caused by grid over-frequency and cold water used at start-up and required an innovative solution to ensure that the plants could continue to operate reliably.