Design and Application for the Method of Static Load Test of Large Tonnage Anchor Pile

2016 
This article focused on engineering existed in the process of large diameter bored pile static load test in the technical difficulties and treatment method. Main girder of the anchor pile and the bearing connection problem,then solved the uneven problem of engineering pile anchor pile reinforcement, finally,solved the difficulties occurred in field engineering,through scientific and meticulous work, perfectly finished the completion of 28000kN single pile static load test task.