Status of the ESS Elliptical Cryomodules at CEA Saclay

2017 
The first ESS prototype cryomodule with medium beta cavities named M-ECCTD is being assembled at CEA Saclay. The Q curves of the 4 cavities mounted inside the cryomodule are presented, and the four power couplers have been conditioned at high power before their assembly onto the cavity string. Completion of the M-ECCTD assembly outside clean room is in progress as well as the finalization of the RF power test stand preparation. RF power tests of the M-ECCTD will be performed during summer 2017. CEA is preparing the production of the ESS medium and high beta cryomodules of the series before the test of the M-ECCTD and the contracts for the procurement of the most critical components have already been signed
    • Correction
    • Source
    • Cite
    • Save
    • Machine Reading By IdeaReader
    0
    References
    0
    Citations
    NaN
    KQI
    []