Geo-mechanics Model Experiment on Underground Cavities of Jingping Hydro-power Station Class-I

2005 
Using geo-mechanical model test the stresses and stability during excavation and construction of the underground cavities of Jingping Hydro-power Station Class-Ⅰ were studied by simulating geo-structure, physical and mechanical features of rock, earth stress, process of excavating cavities and bolt-jetting support. The effects among three different kind of excavating orders and with and without support schemes are compared. It can be assured that all schemes are technically feasible for adopting whichever excavating schemes. Comparatively, second scheme is better than first or third one. The effect of support measures is obvious and they can assure cavities stability and safety.
    • Correction
    • Source
    • Cite
    • Save
    • Machine Reading By IdeaReader
    0
    References
    0
    Citations
    NaN
    KQI
    []